Capital
Building Project - Project Timeline
2002
April 1
- Affirmative Town Meeting vote.
April 22
- Board of Selectmen signs $1.9 million state construction grant.
- RFQ issued for architect.
- First payment of $563,537 of state grant.
July 1
-Architectural contract executed.
-Design development begins.
October 31
-Design development completed.
-Working drawings completed.
-Project goes out for bid.